Time period used in sales order based planning. In the Demand Planning stage, the planner, in cooperation with the customer, enters a demand for the product at customer level.
The customer is then required to confirm the actual demand by placing a firm order within the requirements ascertainment horizon. This is entered into the system as a sales order. After the requirements ascertainment horizon has expired, only the demand (planned independent requirements) for which sales orders exist is converted into production orders.